4.28.2023

Replacement Porter Elementary April 2023 Update

Paving of driveways and parking lots has started. The first portion of the building pad was poured which included the kitchen. A section of the building pad was poured which included the front office area. Concrete is anticipated to be poured every Thursday for the next several weeks until all the building pad and driveways are completed. Materials have begun arriving for the building to rise vertically.