3.28.2024

Construction Begins on Highlands ES

A groundbreaking ceremony was held this month at the site of Highlands Elementary. Earthwork is underway. Gamma Construction has made a lot of progress on the building pad dirt work. Site grading is also going well.





Porter Elementary School Construction Continues

Underground electrical is 99 percent complete. Underground water is complete. Underground plumbing is complete. Sanitary sewer is complete. Storm sewer is complete. Rough grade is 80 percent complete. The building pad is complete. Paving is complete. Sidewalks are 99 percent complete. Masonry is complete. Paint is complete. Site fencing is 98 percent complete. Irrigation and landscaping is 75 percent complete. Fencing is 95 percent complete. Demolition is complete. Site sealant is 75 percent complete. The aluminum canopy is complete. Masons have completed all face brick. Roofers have completed the edge metal/gravel guard and wall caps. Plaster is complete. Mini blinds and shades are installed. 




2.05.2024

Highlands ES Update

February, 2024 - The Board of Trustees awarded a contract to Gamma Construction for the construction of Highlands Elementary School. Construction is scheduled to begin in February.  






1.31.2024

Replacement Porter Elementary January 2024 Update

The sidewalks are 95 percent complete. Tile work is nearly complete except around display cases and fire extinguisher cabinets. Masons completed the face brick at the front of the library. Fencing is 20 percent complete. The aluminum canopy is complete. Underground electricity is 98 percent complete. Roofing is 98 percent complete. The underground water is 99 percent complete. The underground plumbing is 99 percent complete. The sanitary sewer is 99 percent complete.






12.22.2023

Replacement Porter Elementary December 2023 Update

All sheetrock has been installed. Masons have received all brick to complete the masonry approximately during early January. Roofing is 98 percent complete. The underground electric is 98 percent complete. The underground water is 99 percent complete. The underground plumbing is 99 percent complete. The sanitary sewer is 99 percent complete. The storm sewer is 95 percent complete. The rough grade is 80 percent complete. The building pad is complete. The paving is complete. The sidewalks are 40 percent complete.




11.30.2023

Replacement Porter Elementary School November 2023 Update

The underground electric is 98 percent complete. The underground water is 99 percent complete. The underground plumbing is 99 percent complete. The sanitary sewer is 99 percent complete. The storm sewer is 95 percent complete. The rough grade is 80 percent complete. The building pad is complete. The paving is complete. The sidewalks are 40 percent complete.


10.31.2023

Replacement Porter Elementary School October 2023 Update

The underground electric is 98 percent complete. The underground water is 99 percent complete. The underground plumbing is 99 percent complete. The sanitary sewer is 99 percent complete. The storm sewer is 95 percent complete. The rough grade is 80 percent complete. The building pad is complete. The paving is 98 percent complete. The sidewalks are 10 percent complete.