6.30.2022

West Fork High School June 2022 Update

The main building is 87 percent complete. The field house is 78 percent complete. The site work is 85 percent complete. The athletic fields, football/track areas are complete. The baseball and softball artificial turf is under installation. The tennis courts are 85 percent complete. The interior painting is 90 percent complete. The ceramic tile is 85 percent complete. The ceiling grid is 90 percent complete. The ceiling tile is 60 percent complete. The metal panels are 90 percent complete. The air conditioning is 90 percent complete. The plumbing fixtures are 95 percent complete. The lighting is 85 percent complete. The data cabling is 75 percent complete. The kitchen equipment is 95 percent complete. The roofing is 99 percent complete. The windows are 98 percent complete. The topsoil is 20 percent complete. The irrigation system is 60 percent complete. The softball field is 85 percent complete. The baseball field is 85 percent complete. The fencing is 75 percent complete. The gas is 85 percent complete. The road upgrades to Sorters Road are 95 percent complete.