7.28.2022

West Fork High School July 2022 Update

The main building is 95 percent complete. The field house is 88 percent complete. The site work is 90 percent complete. The baseball and softball artificial turf is 80 percent complete. The tennis courts are 90 percent complete. The interior painting is 98 percent complete. The ceramic tile is complete. The ceiling grid is complete. The ceiling tile is complete. The metal panels are complete. The air conditioning is 98 percent complete. The plumbing fixtures are complete. The lighting is 85 percent complete. The data cabling is 95 percent complete. The kitchen equipment is complete. The roofing is complete. The windows are 99 percent complete. The topsoil is complete. The irrigation system is 85 percent complete. The fencing is 95 percent complete. The gas is complete. The road upgrades to Sorters Road are complete.