Overall completion of the main building is at 85 percent. The field house is 70 percent complete. The site work is 80 percent complete. The interior painting is 85 percent complete. The ceramic tile is 65 percent complete. The ceiling grid is 65 percent complete. The ceiling tile is 40 percent complete. The metal panes are 90 percent complete. The air conditioning is 65 percent complete. The plumbing fixtures are 50 percent complete. The lighting is 60 percent complete. The data cabling is 50 percent complete. The kitchen equipment has been delivered and is 60 percent installed. The roofing is 98 percent complete. The windows are 90 percent complete. The topsoil is 20 percent complete. The irrigation is 20 percent complete.The football field turf is complete. The softball field is 65 percent complete. The baseball field is 50 percent complete. The fencing is 15 percent complete. The water service is complete. Natural gas utilities are connected to the building with final pressure testing currently in progress.