Overall completion of the buildings and site work is 78 percent complete. The main building and athletic support facilities are dried in with portions of the main building being air conditioned. All interior partitions are complete with finishes such as painting and ceramic tile in progress. The electrical, plumbing, and HVAC rough-in work is 85 percent complete. The ceiling grid is being installed, allowing the installation of light fixtures, A/C grills, life/safety devices, data, and sound systems to progress. The artificial turf for the football field is 80 percent complete with turf at the baseball and softball fields to follow. The general contractor is distributing topsoil in preparation to begin irrigation and landscaping.