3.08.2022

West Fork High School #3 March Update

The athletic fields and structures are 70 percent complete. The concrete masonry is 65 percent complete. The rough electrical is 80 percent complete. The rough mechanical is 80 percent complete. The rough plumbing is 90 percent complete. The building insulation is 75 percent complete. The windows are 65 percent complete. The interior metal studs are 85 percent complete. The exterior paint is 50 percent complete. The curtain wall is 65 percent complete. The exterior storefront is 90 percent complete. The concrete paving, parking lot and driveways are 95 percent complete. The gas service is 90 percent complete. The water service is 80 percent complete. The sidewalks are 45 percent complete. The interior gypsum board is 65 percent complete. The interior paint is 20 percent complete. The ceramic tile is 10 percent complete. The Sorters Road storm drain is 90 percent complete. The rough grade is 75 percent complete. The pavement is 35 percent complete. The Kingwood Place Extension underground storm drain is complete. The concrete paving is complete. The sidewalks are complete. The striping is five percent complete.