1.27.2022

West Fork High School #3 January Update

The athletic fields and structures are 65 percent complete. The concrete masonry is 55 percent complete. The rough electrical is 75 percent complete. The rough mechanical is 75 percent complete. The rough plumbing is 80 percent complete. The building insulation is 70 percent complete. The exterior sealant is complete. The windows are 50 percent complete. The interior metal studs are 70 percent complete. The exterior metal framing is complete. The exterior paint is 50 percent complete. The curtain wall is 45 percent complete. The exterior storefront is 90 percent complete. The concrete paving parking lot and driveways are 95 percent complete. The electrical service is complete. The gas service is 90 percent complete. The water service is 80 percent complete. The sidewalks are 30 percent complete. The interior gypsum board is 45 percent complete. The interior paint is 10 percent complete. The ceramic tile is five percent complete.