12.14.2021

West Fork High School #3 December Update

The athletic fields and structures are 55 percent complete. The metal deck is complete. The concrete masonry is 40 percent complete. The rough electrical is 50 percent complete, rough mechanical is 55 percent, and rough plumbing is 65 percent complete. The building insulation is 60 percent complete. The lightweight concrete at the roof is complete. The exterior sealant is 90 percent complete. The windows are 40 percent complete. The fireproofing is complete. The interior metal studs are 55 percent complete. The exterior metal framing is 95 percent complete. The exterior paint is 10 percent complete. The curtain wall is five percent complete. The storefront is five percent complete. The concrete paving parking lot and driveways are 80 percent complete. The electrical service is 90 percent complete. The gas service is 90 percent complete. The water service is 80 percent complete.