West Fork High School athletic fields and structures are 45 percent complete. The metal deck is 99 percent complete. The concrete masonry is 30 percent complete. The rough electrical is 30 percent complete, rough mechanical is 40 percent complete, and rough plumbing is 55 percent complete. The building insulation is 50 percent complete. The lightweight concrete on the roof is 98 percent complete. The exterior sealant is 90 percent complete. The windows are 35 percent complete. The fireproofing is 95 percent complete. The interior metal studs are 25 percent complete. The exterior metal framing is 75 percent complete.