Keefer Crossing MS construction is approximately 80 percent complete. The parking lot is 99 percent complete. The exterior masonry is 80 percent complete. The rough mechanical, electrical and plumbing is 95 percent complete. The drywall is 95 percent complete. The ceramic tile is 70 percent complete, paint is 25 percent complete, the ceiling grid is 30 percent complete, and the athletic facilities are 60 percent complete.
At the Comprehensive High School #3, the storm drainage is 90 percent complete. The sanitary sewer is 50 percent complete. The concrete slab at the main building is 65 percent complete. The concrete tilt-up panels are 40 percent complete.