New Keefer Crossing MS and Comprehensive HS #3 January Update

 Keefer Crossing Middle School overall construction is 75 percent complete. The parking lot paving is 95 percent complete. The exterior masonry is 45 percent complete. The interior framing is 90 percent complete, the rough mechanical, electrical, and plumbing is 85 percent complete. The drywall is two percent complete, ceramic tile is 10 percent complete, and paint is 15 percent complete. The ceiling grid is two percent complete. The main football field is 15 percent complete, the track is 20 percent complete, and the fencing is two percent complete.



The New Comprehensive High School #3 site storm drainage is 40 percent complete. The site electrical system is 10 percent complete. The piers are 90 percent complete. The rough plumbing is eight percent complete. The concrete in the main building is 60 percent complete. The parking lot paving is 20 percent complete and the tilt-up panels are two percent complete.