Keefer Crossing Middle School overall construction is 65 percent complete. Site utilities are 95 percent complete. Paving is 90 percent complete. The masonry veneer is 30 percent complete. The interior masonry is 100 percent complete and the interior framing is 85 percent complete. The rough mechanical, electrical, and plumbing is 75 percent complete. The roof at the field house is 80 percent complete and the drywall is five percent complete.
Comprehensive HS #3 land clearing is 100 percent complete. The site storm drainage is 20 percent complete. The main building piers are 85 percent complete. The underground plumbing is five percent complete. The site’s underground electrical utilities are two percent complete.