2.05.2024

Highlands ES Update

February, 2024 - The Board of Trustees awarded a contract to Gamma Construction for the construction of Highlands Elementary School. Construction is scheduled to begin in February.  






1.31.2024

Replacement Porter Elementary January 2024 Update

The sidewalks are 95 percent complete. Tile work is nearly complete except around display cases and fire extinguisher cabinets. Masons completed the face brick at the front of the library. Fencing is 20 percent complete. The aluminum canopy is complete. Underground electricity is 98 percent complete. Roofing is 98 percent complete. The underground water is 99 percent complete. The underground plumbing is 99 percent complete. The sanitary sewer is 99 percent complete.






12.22.2023

Replacement Porter Elementary December 2023 Update

All sheetrock has been installed. Masons have received all brick to complete the masonry approximately during early January. Roofing is 98 percent complete. The underground electric is 98 percent complete. The underground water is 99 percent complete. The underground plumbing is 99 percent complete. The sanitary sewer is 99 percent complete. The storm sewer is 95 percent complete. The rough grade is 80 percent complete. The building pad is complete. The paving is complete. The sidewalks are 40 percent complete.




11.30.2023

Replacement Porter Elementary School November 2023 Update

The underground electric is 98 percent complete. The underground water is 99 percent complete. The underground plumbing is 99 percent complete. The sanitary sewer is 99 percent complete. The storm sewer is 95 percent complete. The rough grade is 80 percent complete. The building pad is complete. The paving is complete. The sidewalks are 40 percent complete.


10.31.2023

Replacement Porter Elementary School October 2023 Update

The underground electric is 98 percent complete. The underground water is 99 percent complete. The underground plumbing is 99 percent complete. The sanitary sewer is 99 percent complete. The storm sewer is 95 percent complete. The rough grade is 80 percent complete. The building pad is complete. The paving is 98 percent complete. The sidewalks are 10 percent complete. 






9.27.2023

Replacement Porter Elementary School September 2023 Update

The underground electric is 95 percent complete. The underground water is 99 percent complete. The underground plumbing is 95 percent complete. The sanitary sewer is 95 percent complete. The storm sewer is 95 percent complete. The rough grade is 80 percent complete. The building pad is complete. The paving is 98 percent complete. Interior masonry is 95 percent complete. Metal stud framing on the building exterior is 98 percent complete. Earthwork has started on Loop 494 turning lanes.






8.31.2023

Replacement Porter Elementary School August 2023 Update

The underground electric is 95 percent complete. The underground water is 99 percent complete. The underground plumbing is 75 percent complete. The sanitary sewer is 95 percent complete. The storm sewer is 90 percent complete. The rough grade is 80 percent complete. The building pad is complete. The paving is 90 percent complete. The fireproofing is complete.