7.20.2020

Land Clearing Begins on Comprehensive HS #3

The site has been cleared and rough grading is at 90 percent completion. The building pad is complete. The general contractor will start installing the concrete piers concurrent with the underground storm and sanitary systems.


5.21.2020

Keefer Crossing Middle School Construction Underway

The NCISD Board of Trustees approved an award of construction contract May 18 for the New Comprehensive High School #3 to Gamma Construction. Construction is scheduled to begin within two to three weeks.

Also, construction at Keefer Crossing Middle School is progressing well with overall completion at 22 percent. The parking lot paving is at 75 percent, the building foundation is 65 percent complete, and the structural steel is 18 percent complete.


Also, the Woodridge Forest Middle School addition is nearly complete. The campus furniture and equipment is scheduled to be delivered in late June.

4.23.2020

Woodridge Forest MS Addition Enters Final Stages of Construction

The Woodridge Forest Middle School addition has entered the final stages of construction. The project is 99 percent complete with the contractor finishing up the punch list. Furniture, fixtures and equipment has been ordered and is expected to be delivered in June.


Keefer Crossing Middle School construction is on schedule and 16 percent complete. Most of the underground drainage system is complete along with 50 percent of the parking lot. The foundation is 40 percent complete allowing the erection of the structural steel to start.

New Caney ISD received six proposals from general contractors on April 7, 2020 for construction of the Comprehensive High School #3. The District is in the process of reviewing the contractors’ proposals and a recommendation is expected to be submitted to the Board of Trustees in May 2020. Campus construction would start in June.

2.14.2020

Woodridge Forest Middle School Expansion Nears Completion

Construction is nearly complete at Woodridge Forest Middle School, while progress continues with the new Keefer Crossing Middle School campus and comprehensive high school #3.

The Woodridge Forest MS addition construction is 80-percent complete overall with exterior work at 95 percent complete and interior work at 90 percent complete. The interior finishes are complete except the flooring and ceiling tile. The HVAC, electrical and plumbing are 95 percent complete. The project is on schedule for completion May 2020 and for furniture to be delivered in June 2020.





Keefer Crossing MS construction is slightly behind schedule due to the inclement weather but will not affect the final completion date. The grading work is 90 percent complete, underground storm piping 20 percent complete, structural concrete piers at the main building 98 percent complete with piers at the field house in progress. The perimeter grade beams are at 10 percent completion.




Design for the comprehensive high school #3 is complete. The project will be out for proposal in March 2020.






12.09.2019

Woodridge Forest Middle School Expansion Progressing on Schedule

Construction projects are moving forward at Woodridge Forest Middle School, Keefer Crossing Middle School, and the new comprehensive high school #3.

Construction at Woodridge Forest Middle School is 65 percent complete. The exterior masonry is 98 percent complete and the window installation is 75 percent complete. The interior work that includes mechanical, electrical, and plumbing engineering is 85 percent complete. The gypsum board installation is 90 percent complete, painting is 30 percent complete, and the ceiling is 15 percent complete.



Keefer Crossing Middle School construction is in its early stages but construction has begun. The site grading is 50 percent complete and the building pad is 40 percent complete.



The NCISD Transportation Department expansion is finished. A new entrance was added to the facility from Antique Lane along with more parking for school buses.



The new comprehensive high school #3 design is 95 percent complete. Construction is scheduled to go out for bid in February 2020.

10.10.2019

Board Approves Contract for Construction of New Keefer Crossing Middle School

The New Caney ISD Board of Trustees approved a contract for construction services for Keefer Crossing Middle School at its regular meeting Sept. 16. Construction begins this month on the new 221,650 square-foot campus and is scheduled to be completed in the summer of 2021. The new campus will have an additional 450 new seats for a capacity of 1,500 students.


In other bond construction, the NCISD Transportation Department parking lot expansion is 85 percent complete with final completion scheduled for mid-October.


7.24.2019

Construction progressing at Woodridge Forest Middle School

Construction is progressing on the expansion at Woodridge Forest Middle School. Classroom additions have their underground drainage and the concrete foundation complete. The structural steel is 50 percent complete. The physical education addition has its underground drainage and concrete foundation complete. The masonry is 98 percent complete, waterproofing is 90 percent complete, roof is 90 percent complete, and the exterior insulation is 70 percent complete. The bleacher expansion foundation is 50 percent complete. The existing campus new fire alarm is 39 percent complete and the Acrovyn wall cover is 10 percent complete.


Also, design is complete for the new middle school. Construction documents are 95 percent complete. For comprehensive high school #3, the schematic design is 100 percent complete and the design development is 50 percent complete. Finally, rough grading for an expansion of the transportation facility is 100 percent complete. The underground drainage is 90 percent complete. The underground electrical system is 70 percent complete. The retention pond expansion is 45 percent complete. The storm-water lift station is 20 percent complete.