3.28.2024

Porter Elementary School Construction Continues

Underground electrical is 99 percent complete. Underground water is complete. Underground plumbing is complete. Sanitary sewer is complete. Storm sewer is complete. Rough grade is 80 percent complete. The building pad is complete. Paving is complete. Sidewalks are 99 percent complete. Masonry is complete. Paint is complete. Site fencing is 98 percent complete. Irrigation and landscaping is 75 percent complete. Fencing is 95 percent complete. Demolition is complete. Site sealant is 75 percent complete. The aluminum canopy is complete. Masons have completed all face brick. Roofers have completed the edge metal/gravel guard and wall caps. Plaster is complete. Mini blinds and shades are installed.