Keefer Crossing Middle School

Design: Summer 2018 - Summer 2019
Bid Process: Fall 2019 - Winter 2020
Construction: Spring 2020 - Summer 2021 (complete)

UPDATES:

August, 2021 - Keefer Crossing Middle School is substantially complete and opened for staff and students on the first day of school Aug. 9. The contractor is working on a list of items that will be completed on weekends.








July, 2021 - Keefer Crossing Middle School is 92 percent complete overall. The rough mechanical, electrical, and plumbing is 98 percent complete. The mechanical finish is 85 percent complete. The electrical finish is 75 percent complete. The plumbing is 85 percent complete. The ceramic tile is 100 percent complete. The paint is 88 percent complete. The ceiling grid is 95 percent complete and the ceiling tile is 85 percent complete. The athletic fields are 90 percent complete.







June, 2021 - The new Keefer Crossing Middle School is 88 percent complete overall. The exterior masonry is complete. The rough mechanical, electrical, and plumbing is 98 percent complete. The mechanical finish is 65 percent complete. The electrical finish is 60 percent complete. The plumbing is 60 percent complete. The drywall is complete. The ceramic tile is 90 percent complete. The paint is 75 percent complete. The ceiling grid is 80 percent complete. The athletic fields are 90 percent complete. 



May, 2021 - Overall construction at the new Keefer Crossing Middle School is 86 percent complete. The exterior masonry is 95 percent complete. The rough mechanical, electrical, and plumbing is 98 percent complete. The mechanical finish is 55 percent complete. The electrical finish is 40 percent complete. The plumbing is 40 percent complete. The drywall is 90 percent complete. The ceramic tile is 85 percent complete. The paint is 70 percent complete and the ceiling grid is 65 percent complete. The athletics facilities are 85 percent complete. 






April, 2021 - Overall construction at the new Keefer Crossing Middle School campus is 83 percent complete. The parking lot is 99 percent complete. The exterior masonry is 88 percent complete. The rough mechanical, electrical, and plumbing is 95 percent complete. The mechanical finish is 40 percent complete, electrical finish is 30 percent complete, and finish plumbing is 20 percent complete. The drywall is 85 percent complete, ceramic tile is 75 percent complete, paint is 60 percent complete, and ceiling grids are 50 percent complete. The athletic facilities are 75 percent complete. Watch the updated drone footage video below.



March, 2021 - Keefer Crossing MS construction is approximately 80 percent complete. The parking lot is 99 percent complete. The exterior masonry is 80 percent complete. The rough mechanical, electrical and plumbing is 95 percent complete. The drywall is 95 percent complete. The ceramic tile is 70 percent complete, paint is 25 percent complete, the ceiling grid is 30 percent complete, and the athletic facilities are 60 percent complete.  






January, 2021 - Keefer Crossing Middle School overall construction is 75 percent complete. The parking lot paving is 95 percent complete. The exterior masonry is 45 percent complete. The interior framing is 90 percent complete, the rough mechanical, electrical, and plumbing is 85 percent complete. The drywall is two percent complete, ceramic tile is 10 percent complete, and paint is 15 percent complete. The ceiling grid is two percent complete. The main football field is 15 percent complete, the track is 20 percent complete, and the fencing is two percent complete.





December, 2020 - Keefer Crossing Middle School overall construction is 65 percent complete. Site utilities are 95 percent complete. Paving is 90 percent complete. The masonry veneer is 30 percent complete. The interior masonry is 100 percent complete and the interior framing is 85 percent complete. The rough mechanical, electrical, and plumbing is 75 percent complete. The roof at the field house is 80 percent complete and the drywall is five percent complete.





November, 2020 - Watch this drone video footage of construction at Keefer Crossing Middle School site. 



October, 2020 - Keefer Crossing Middle School overall construction is 45 percent complete, site paving is 85 percent complete, site utilities are 90 percent complete, and structural steel is 100 percent complete. The masonry - brick veneer is two percent complete, the interior concrete masonry unit is 90 percent complete, the interior wall framing is 75 percent complete, and the rough mechanical, electrical, and plumbing is 65 percent complete. Roofing at the main building is 98 percent complete. Roofing at the field house is 40 percent complete.




September, 2020 - Keefer Crossing Middle School site paving is 80 percent complete. The structural steel is 95 percent complete, masonry is 20 percent complete, storm and sewer site utilities are 95 percent complete and the rough mechanical and electrical installation is 18 percent complete.
 
August, 2020 - The site paving at Keefer Crossing Middle School is 50 percent complete. The structural steel installation is 90 percent complete, roof decking installation is 90 percent complete, and masonry installation is at 15 percent. The site utilities installation is at 85 percent. The rough mechanical, electrical, and plumbing installation is at 15 percent. 



July, 2020 - Construction is progressing as scheduled and is 33 percent complete. The structural steel installation is virtually complete and roof decking installation is 45 percent complete. The exterior masonry and steel framing has started along with the plumbing, electrical and HVAC rough-in work.





May, 2020 - Construction at Keefer Crossing Middle School is progressing well with overall completion at 22 percent. The parking lot paving is at 75 percent, the building foundation is 65 percent complete, and the structural steel is 18 percent complete.



April, 2020 - Keefer Crossing Middle School construction is on schedule and 16 percent complete. Most of the underground drainage system is complete along with 50 percent of the parking lot. The foundation is 40 percent complete allowing the erection of the structural steel to start.

February, 2020 - Keefer Crossing MS construction is slightly behind schedule due to the inclement weather but will not affect the final completion date. The grading work is 90 percent complete, underground storm piping 20 percent complete, structural concrete piers at the main building 98 percent complete with piers at the field house in progress. The perimeter grade beams are at 10 percent completion.




December, 2019 - Keefer Crossing Middle School construction is in its early stages but construction has begun. The site grading is 50 percent complete and the building pad is 40 percent complete.



October, 2019 - The New Caney ISD Board of Trustees approved a contract for construction services for Keefer Crossing Middle School at its regular meeting Sept. 16. Construction begins this month on the new 221,650 square-foot campus and is scheduled to be completed in the summer of 2021. The new campus will have an additional 450 new seats for a capacity of 1,500 students.



July, 2019 - The design is complete for the new middle school. Construction documents are 95 percent complete.

April, 2019 - The site of the replacement campus for Keefer Crossing Middle School is located on Gene Campbell Road in New Caney.





February, 2019 - IBI Architects provided the Board of Trustees a design update at the February regular meeting. Design of the school is nearing completion. The design is an adaption of the Woodridge Forest Middle School building, with some modifications, including a different front elevation and a third-floor classroom wing. The campus will include a field house, lighted football field, 8-lane track, and a practice field. Work on construction documents will begin early this spring with construction bids going out this summer. Located at 21460 Gene Campbell Road, the school is scheduled to open in August 2021. The name of the new middle school will remain Keefer Crossing Middle School. 






July, 2018 - The New Caney ISD Board of Trustees awarded a contract to IBI Architects for services to design and construct a new middle school facility at its regular meeting in July. The facility, part of the 2018 bond program approved by voters in May, will be a replacement campus for Keefer Crossing Middle School.