Replacement Porter Elementary School July 2023 Update

The structural steel is 95 percent complete. The roof decking is 55 percent complete. The concrete paving is 99 percent complete. The HVAC installation is 20 percent complete. The plumbing, electrical rough-ins, and metal studs are 10 percent complete. The masonry is 33 percent complete. The fireproofing is 65 percent complete.