6.29.2023

Replacement Porter Elementary June 2023 Update

The structural steel is 50 percent complete. The roof decking is 40 percent complete. The concrete paving is 90 percent complete. The HVAC installation will start soon. The plumbing and electrical rough-ins and metal stud installation will start soon. Masonry is five percent complete.