The new Keefer Crossing Middle School is 88 percent complete overall. The exterior masonry is complete. The rough mechanical, electrical, and plumbing is 98 percent complete. The mechanical finish is 65 percent complete. The electrical finish is 60 percent complete. The plumbing is 60 percent complete. The drywall is complete. The ceramic tile is 90 percent complete. The paint is 75 percent complete. The ceiling grid is 80 percent complete. The athletic fields are 90 percent complete.
West Fork High School, the name selected for the new comprehensive High School #3, site work storm drainage is 95 percent complete. The sanitary sewer system is 85 percent complete. The electrical system is 98 percent complete. The water system is 90 percent complete. The building concrete slab is 90 percent complete. The form and pour tilt-up panels are 99 percent complete. The erect panels are 95 percent complete. The structural steel is 55 percent complete. The metal decking is 20 percent complete. The concrete masonry unit masonry is 10 percent complete.