The NCISD Board of Trustees approved an award of construction contract May 18 for the New Comprehensive High School #3 to Gamma Construction. Construction is scheduled to begin within two to three weeks.
Also, construction at Keefer Crossing Middle School is progressing well with overall completion at 22 percent. The parking lot paving is at 75 percent, the building foundation is 65 percent complete, and the structural steel is 18 percent complete.
Also, the Woodridge Forest Middle School addition is nearly complete. The campus furniture and equipment is scheduled to be delivered in late June.