Brookwood Forest Elementary construction progressing

Construction of New Caney ISD's 11th elementary school is well underway. Brookwood Forest Elementary School, scheduled to open for the 2018-19 school year, is approximately 20% complete overall. The foundation is 80% complete, and structural steel is 85% complete. The exterior wall framing has begun. Also, the district natatorium is nearing completion (approximately 95% complete), and Infinity Early College High School's new facility is 85% complete overall.  