New Caney Middle School

Design: Summer 2016 - Spring 2017 (revised)
Bid Process: Spring 2017 (revised)
Construction: Spring 2017 - Summer 2018 (complete)

UPDATES:

August, 2018 - Renovations and additions at New Caney Middle School are complete. Work included kitchen/cafeteria expansion and upgrades, a pre-ag classroom addition, fine arts expansion, updates to the auditorium, and other life cycle items.



July, 2018 - The cafeteria expansion is 75% complete and the kitchen addition is 85% complete. The Fine Arts addition, which includes areas for choir, drama, orchestra, and dance, is 90% complete. A campus-wide, new, central air conditioning and electrical system is 80% complete. The renovations are expected to be complete by August. 





February, 2018 - Work at New Caney Middle School is approximately 28% complete overall. Exterior masonry is 55% complete and work on mechanical, electrical, and plumbing has begun along with interior walls. 






December, 2017 - The fine arts and kitchen addition are approximately 20% complete overall. Structural steel is about 80% complete. Exterior construction will begin in January. 




 September, 2017 - Renovation work is complete, including painting and new carpet. The fine arts and kitchen addition are 10% complete overall with foundation work in progress. Site work is 30% complete.  





July, 2017 - Construction began this month on additions and renovations at New Caney Middle School. Work on the fine arts expansion has begun, and the cafeteria/kitchen expansion is approximately 10% complete overall. 




January, 2017 - Design development is complete, and the project is scheduled to go out to bid in March. 

November, 2016 - Design development is approximately 95% complete, and work on construction drawings has begun. 

September, 2016 - Design is 35% complete, and floor plans for renovations have been finalized. 


June, 2016 - The Board of Trustees approved an agreement for design/construction delivery method to Joiner Partnership, Inc. for additions and renovations at New Caney Middle School at its June regular meeting. Work at New Caney Middle School will include kitchen/cafeteria expansion and upgrades, a pre-ag classroom addition, fine arts expansion, updates to the auditorium, and other life cycle items. The tentative timeline for completion is late fall 2017. 

August, 2016 - NCISD Director of Facility Planning and Construction Richard Gates reported to the Board that the design for work at NCMS is approximately 20% complete. 



progressing with design, 35% complete... floorplans have been finalized