Replacement Porter Elementary January 2024 Update

The sidewalks are 95 percent complete. Tile work is nearly complete except around display cases and fire extinguisher cabinets. Masons completed the face brick at the front of the library. Fencing is 20 percent complete. The aluminum canopy is complete. Underground electricity is 98 percent complete. Roofing is 98 percent complete. The underground water is 99 percent complete. The underground plumbing is 99 percent complete. The sanitary sewer is 99 percent complete.