11.30.2023

Replacement Porter Elementary School November 2023 Update

The underground electric is 98 percent complete. The underground water is 99 percent complete. The underground plumbing is 99 percent complete. The sanitary sewer is 99 percent complete. The storm sewer is 95 percent complete. The rough grade is 80 percent complete. The building pad is complete. The paving is complete. The sidewalks are 40 percent complete.