9.27.2023

Replacement Porter Elementary School September 2023 Update

The underground electric is 95 percent complete. The underground water is 99 percent complete. The underground plumbing is 95 percent complete. The sanitary sewer is 95 percent complete. The storm sewer is 95 percent complete. The rough grade is 80 percent complete. The building pad is complete. The paving is 98 percent complete. Interior masonry is 95 percent complete. Metal stud framing on the building exterior is 98 percent complete. Earthwork has started on Loop 494 turning lanes.