Construction Continues On Track at New Keefer Crossing MS and Comprehensive High School #3

Construction continues on track at the new Keefer Crossing Middle School campus and the third comprehensive high school.

The site paving at Keefer Crossing Middle School is 50 percent complete. The structural steel installation is 90 percent complete, roof decking installation is 90 percent complete, and masonry installation is at 15 percent. The site utilities installation is at 85 percent. The rough mechanical, electrical, and plumbing installation is at 15 percent. 

The third comprehensive high school site clearing is 85 percent complete. The rough grading, the process of making a level or slope base, is 45 percent complete. Watch the video below for drone footage of both construction sites.