The first phase of renovations at New Caney High School are complete, including the band hall, the cosmetology center, physical education area, and additional classrooms. The next phase is beginning and includes areas for choir, orchestra, and drama.
Work at New Caney Middle School is approximately 28% complete overall. Exterior masonry is 55% complete and work on mechanical, electrical, and plumbing has begun along with interior walls.
Construction of Brookwood Forest Elementary is approximately 48% complete overall. Exterior walls are about 85% complete, and some interior finishes have begun. Paving has also begun.