5.17.2017

Board approves construction contract for work at New Caney Middle School, other projects continue

The New Caney ISD Board of Trustees awarded a construction contract for renovations at New Caney Middle School to Division One Construction at its regular meeting this month. Work at New Caney Middle School will include kitchen/cafeteria expansion and upgrades, a pre-ag classroom addition, fine arts expansion, updates to the auditorium, and other life cycle items. The current timeline for completion is summer 2018. 

Also, Dogwood Elementary, set to open in August, is approximately 85% complete overall. Work continues on interior finishes, including carpet, tile, painting, and plumbing fixtures. Also, the final site landscaping is in progress. 


Dogwood Elementary School 
Dogwood Elementary School
Dogwood Elementary School
Dogwood Elementary School

Also, construction of Infinity Early College High School is approximately 40% complete overall. Work on the exterior wall system is 80% complete while interior walls, plumbing, and electrical work is 40% complete.


Infinity Early College High School

Also, work at Kings Manor Elementary School is approximately 60% complete overall. The cafeteria/kitchen addition is dried in and interior finishes are in progress.