9.20.2016

Elementary #10 foundation, parking lot nearing completion

NCISD Director of Facility Planning and Construction Richard Gates reported to the Board of Trustees at its regular meeting in September that construction of Elementary School #10 is proceeding on schedule. The school is approximately 18% complete overall. The building foundation and parking lot are both nearing completion while work on the structural steel is approximately 40% complete. Builders will be starting the exterior framing and rough interior work this month.

Elementary School #10
Elementary School #10

Also, renovations at Porter High School are approximately 18% complete overall with 100% of the foundation work for the classroom building addition and the agriculture facility complete. The aquatic center at the site of Texan Drive Stadium is approximately 10% complete, and excavation for the addition at Kings Manor Elementary is underway.

Porter High School
Porter High School
Aquatic Center
Kings Manor Elementary