NCISD Director of Facility Planning and Construction Richard Gates reported to the Board of Trustees at its regular meeting in September that construction of Elementary School #10 is proceeding on schedule. The school is approximately 18% complete overall. The building foundation and parking lot are both nearing completion while work on the structural steel is approximately 40% complete. Builders will be starting the exterior framing and rough interior work this month.
 |
Elementary School #10 |
 |
Elementary School #10 |
Also, renovations at Porter High School are approximately 18% complete overall with 100% of the foundation work for the classroom building addition and the agriculture facility complete. The aquatic center at the site of Texan Drive Stadium is approximately 10% complete, and excavation for the addition at Kings Manor Elementary is underway.
 |
Porter High School |
 |
Porter High School |
 |
Aquatic Center |
 |
Kings Manor Elementary |