9.24.2021

West Fork High School #3 September Update

West Fork High School storm drain is 95 percent complete. The sanitary sewer system is 90 percent complete. The electrical system is 98 percent complete. The water system is 90 percent complete. The athletic fields are 35 percent complete. At the main building, the concrete slab is 100 percent complete. The structural steel is 100 percent complete. The metal decking is 98 percent complete. The concrete masonry unit is 25 percent complete. The rough electrical is 15 percent complete. The rough mechanical is 35 percent complete. The rough plumbing is 50 percent complete. The building insulation is 30 percent complete. The rough lightweight concrete is 95 percent complete. The exterior building sealant is 50 percent complete. The windows are 30 percent complete. The fireproofing is 90 percent complete.