7.26.2021

New Keefer Crossing MS and West Fork HS #3 July Update

Keefer Crossing Middle School is 92 percent complete overall. The rough mechanical, electrical, and plumbing is 98 percent complete. The mechanical finish is 85 percent complete. The electrical finish is 75 percent complete. The plumbing is 85 percent complete. The ceramic tile is 100 percent complete. The paint is 88 percent complete. The ceiling grid is 95 percent complete and the ceiling tile is 85 percent complete. The athletic fields are 90 percent complete.




West Fork High School storm drainage is 95 percent complete. The sanitary sewer system is 85 percent complete. The electrical system is 98 percent complete. The water system is 90 percent complete. The building concrete slab is 92 percent complete. The form and pour tilt-up panels are 100 percent complete. The erect panels are 100 percent complete. The structural steel is 75 percent complete. The metal decking is 25 percent complete. The concrete masonry unit masonry is 15 percent complete. The rough electrical is five percent complete. The rough mechanical is two percent complete. The exterior building sealant is 20 percent complete.