Technology/Security

Design: Summer 2015 - Fall 2015
Bid Process: Fall 2015
Construction: Fall 2015 - Summer 2016 (complete)

UPDATES:

September, 2016 - The installation of additional security cameras and the hardware for the keyless entry system on all campuses is complete. 

August, 2016 - NCISD Director of Facility Planning and Construction Richard Gates reported to the Board at its regular August meeting that security upgrades (new, additional cameras and keyless building access systems) are approximately 95% complete. 

July, 2016 - NCISD Director of Facility Planning and Construction Richard Gates reported to the Board at its regular July meeting that security upgrades (new, additional cameras and keyless building access systems) are on schedule for completion in August. 

June, 2016 - Director of Facility Planning and Construction Richard Gates reported to the Board of Trustees at its June regular meeting that installation of updated security cameras across the district is approximately 80% complete. Security updates, which also include a card building-access system, is scheduled to be complete in August. 

March, 2016 - Director of Facility Planning and Construction Richard Gates reported to the Board of Trustees at its March, 2016 regular meeting that installation of updated security cameras and card access systems will begin in April. The work is scheduled to be complete this summer. 

January, 2016 - The New Caney ISD Board of Trustees awarded the construction contract for installation of new/additional security cameras and card access systems to Digital Air Control at its regular meeting Jan. 18, 2016. The installation of new/additional cameras and card access systems will take place at 17 facilities across the district and is scheduled to be complete in the summer of 2016.

December, 2015 - NCISD Director of Facility Planning and Construction Richard Gates reported to the Board of Trustees at its December 14, 2015 meeting that bids had been received for keyless-entry, card-reader access systems to be implemented at all of the district’s schools. Gates informed the Board that the district would likely present a contract recommendation for the work to the Board at its regular meeting in January.

November, 2015 - NCISD Director of Facility Planning and Construction Richard Gates reported to the Board of Trustees at its November 16, 2015 meeting that card readers for facility access would be going out to bid in November and to the Board after the first of the year for approval.

June, 2015 - The installation of a card access control system, along with the installation and updating of security cameras, across the district is planned to occur in the first phase of projects associated with the 2015 bond election. Project timeline dates are set for planning and project-management purposes and may be adjusted in response to changing circumstances as work progresses.
  • Design: Summer 2015 - Fall 2015
  • Bid Process: Fall 2015
  • Construction: Fall 2015 - Summer 2016