Early College HS

Design: Summer 2015 - Spring 2016
Bid Process: Spring 2016 - Summer 2016
Construction: Fall 2016 - Winter 2017 (adjusted time-frame)

UPDATES:

May, 2017 - Construction of Infinity Early College High School is approximately 40% complete overall. Work on the exterior wall system is 80% complete while interior walls, plumbing, and electrical work is 40% complete.





April, 2017 - Photo update for construction of Infinity Early College High School.





March, 2017 - The project is approximately 15% complete overall. Structural steel and framing is complete, and work has begun on exterior walls and roof decking.





February, 2017 - Photo update for Infinity Early College High School, scheduled to open in the winter of 2017.





January, 2017 - Construction of the new campus is underway. The building foundation and the parking lot are each approximately 60% complete while site utilities including the retention pond, water, and sewer are 40% complete.  





October, 2016 - The New Caney ISD Board of Trustees awarded a construction contract for Infinity Early College High School to Pepper Lawson Construction at its regular meeting this month. Design of the early college campus was completed at the end of the summer. 





September, 2016 - Design is complete, and the project went out to bid this month with a bid date of September 29.

June, 2016 - Director of Facility Planning and Construction Richard Gates reported to the Board of Trustees at its June regular meeting that construction documents for the early college high school are approximately 75% complete. Bids for construction are scheduled to go out in September of this year. 

April, 2016 - Director of Facility Planning and Construction Richard Gates reported to the Board of Trustees at its April regular meeting that design of the early college high school is approximately 80% complete. 

March, 2016 - Director of Facility Planning and Construction Richard Gates reported to the Board of Trustees at its March, 2016 regular meeting that design for the early college campus is 30% complete. 

February, 2016 - The New Caney ISD Board of Trustees gave the district authorization to negotiate and execute a final sale and purchase agreement for land for the early college high school.

June, 2015 - The construction of an early college high school is planned to occur in the first phase of projects associated with the 2015 bond election. Project timeline dates are set for planning and project-management purposes and may be adjusted in response to changing circumstances as work progresses.
  • Design: Summer 2015 - Spring 2016
  • Bid Process: Spring 2016 - Summer 2016
  • Construction: Spring 2016 - Summer 2017


out to bid with date of sept. 29 bid date... held pre bid meeting with 10 general contractors showing interest... design is complete and went to bid